On this AON diagram, if activity F is crashed by 5 days, what would be the new length of the project?

A. 42
B. 79
C. 59
D. 49
E. 48
F. 20

Answer :

The new length of the project if activity F is crashed by 5 days will be 440 days

Activity F is represented by a duration of 12 days.

If the activity is crashed by 5 days, the new length of the project will be calculated as follows:

Total duration = Sum of all activities in the critical path.

Initial duration = 42 + 79 + 59 + 49 + 48 + 20 + 12 + 89 + 5 + 10 + 12

= 484

New Duration of Activity F = 12 - 5

= 7

New Total Duration = 42 + 79 + 59 + 49 + 48 + 20 + 7 + 89 + 5 + 10 + 12

= 440

To learn more on length:

https://brainly.com/question/2217700

#SPJ11

Complete Question : Image attached