Answer :
Final answer:
The labor will cover a total of 1080 hours over the course of four weeks in the project.
Explanation:
The subject of this question is mathematics and it deals with the concept of percentage and hours calculation. First, let's consider the total number of hours the project is budgeted for, which is 1200 hours. In the first two weeks, the labor covered 30% of the workload, which amounts to 0.30*1200 = 360 hours. Then, in the final two weeks, the labor covered 60% of the workload which equals 0.60*1200 = 720 hours. So, the labor will cover a total of 360 hours + 720 hours = 1080 hours in the whole project over the course of four weeks.
Learn more about Percentage here:
https://brainly.com/question/32197511
#SPJ1