What improvement tool would a project team use to identify who is responsible for each step of a process?

A. Pareto Chart
B. Ishikawa Diagram
C. RACI Matrix
D. Scatter Diagram

Answer :

Final answer:

The correct answer is c) RACI Matrix.The improvement tool that a project team would use to identify who is responsible for each step of a process is the RACI Matrix.

Explanation:

The improvement tool that a project team would use to identify who is responsible for each step of a process is the RACI Matrix. The RACI Matrix is a responsibility assignment matrix that helps define roles and responsibilities within a project team. It stands for Responsible, Accountable, Consulted, and Informed.

In an RACI Matrix, each task or step of the process is listed, and for each task, the matrix specifies who is Responsible for completing it, who is Accountable for ensuring its completion, who should be Consulted for their input, and who should be Informed of its progress. This helps ensure clear communication and accountability within the project team.

For example, in a software development project, the RACI Matrix may show that the developer is Responsible for writing the code, the project manager is Accountable for overseeing the development process, the quality assurance team should be Consulted for testing input, and the stakeholders should be Informed of the project progress.