Answer :
The total quantity of direct materials to be purchased is 100,300 pounds.
The total quantity of direct materials to be purchased can be calculated by adding the desired ending direct materials to the direct materials required for production and subtracting the beginning direct materials.
Desired ending direct materials: 19,000 pounds
Direct materials required for production: 95,000 pounds
Beginning direct materials: 14,700 pounds
To calculate the total quantity of direct materials to be purchased:
Total quantity = Desired ending direct materials + Direct materials required for production - Beginning direct materials
Total quantity = 19,000 + 95,000 - 14,700
Total quantity = 100,300 pounds
So, the total quantity of direct materials to be purchased is 100,300 pounds.
To calculate the total quantity of direct materials to be purchased, we need to consider the desired ending direct materials, direct materials required for production, and beginning direct materials. In this case, the desired ending direct materials are 19,000 pounds, the direct materials required for production are 95,000 pounds, and the beginning direct materials are 14,700 pounds. By adding the desired ending direct materials and the direct materials required for production, and then subtracting the beginning direct materials, we get the total quantity of direct materials to be purchased, which is 100,300 pounds.
The total quantity of direct materials to be purchased is 100,300 pounds, according to the given information.
To know more about purchased visit :
https://brainly.com/question/32961485
#SPJ11