Answer :
Project managers can use it to identify potential project delays and address them promptly.
Here are the solutions to the given multiple-choice questions:
Successor activity will start 5 days after the predecessor activity finishes is the correct option. In project management, scheduling activities or tasks with a time lag is common. Start-to-start is one such scheduling approach in which the next task starts only after the previous task starts. However, in this approach, a lag time is introduced between the start of the current and the previous activity.
Crashing the schedule is the correct option. Crashing is a method of accelerating a project schedule without sacrificing its scope. By minimizing the duration of each task and reducing the project's time, the project manager attempts to complete the project on time.
It provides a graphical view of dependencies among activities is the correct option. Precedence Diagramming Method (PDM) is a visual representation of project dependencies. The project manager can easily see the task's predecessors and successors in a graphical format. As a result, project managers can use it to identify potential project delays and address them promptly.
Learn more about Project managers visit:
brainly.com/question/31545760