Answer :
The job of adding texture to the walls of the virtual environment will take approximately 16 hours to complete, considering 4 walls per room, 6 rooms per building, and 8 buildings.
To determine how many hours it will take to add texture to the walls of the virtual environment, we need to calculate the total time required for the job.
First, let's find the total number of walls in the virtual environment. We know that there are 4 walls per room, 6 rooms per building, and 8 buildings. To calculate the total number of walls, we can multiply these numbers together:
4 walls/room * 6 rooms/building * 8 buildings = 192 walls
Next, we need to determine the time it takes to texture each wall. According to the information given, each wall takes 5 minutes.
To find the total time required for the job, we multiply the time it takes to texture each wall by the total number of walls:
5 minutes/wall * 192 walls = 960 minutes
To convert the minutes to hours, we divide the total minutes by 60:
960 minutes / 60 = 16 hours
Therefore, the job will take approximately 16 hours to complete.