Answer :
Ryan rate = 1/5 job/hr
Castel rate = 1/6 job/hr
Together rate = 1/x job/hr
Equation:
1/5 + 1/6 = 1/x
6x + 5x = 30
11x = 30
x = 2 8/11 hr = 2 hr (8/11)60 = 2hr 47 minutes (time to do the job together)