Which is not one of the AIACC's three major value propositions for IPD?

1. Flexibility
2. Less Litigation
3. Speed
4. Collaboration

Answer :

Flexibility is not specifically listed as one of the AIACC's three major value propositions for Integrated Project Delivery (IPD), which are collaboration, speed, and less litigation. However, flexibility could be seen as a potential outcome of these propositions. Option 1) Flexibility is the right answer.

The AIACC's major value propositions for Integrated Project Delivery (IPD) typically include aspects such as collaboration, speed, and reduced litigation, which are meant to enhance efficiency and innovation in project delivery. The value proposition of flexibility is not specifically listed as one of the three major propositions for IPD. IPD is structured to facilitate a more seamless and cooperative environment that can lead to the acceleration of learning, add value to knowledge production, generate cost savings, enhance quality, and spur innovation through collaboration. Although flexibility can be a resultant benefit of this process, it is not highlighted as a foundational value proposition of the AIACC's approach to IPD. Option 1) Flexibility is the right answer.