High School

The single milling machine at Stout Manufacturing was severely overloaded last year. The plant operates eight hours per day, five days per week, and 50 weeks per year. Management prefers a capacity cushion of 15 percent.

Two major types of products are routed through the milling machine:

- The annual demand for product A is 3000 units, with a batch size of 20 units. The standard processing time for A is 0.5 hours/unit, and the standard setup time is 2 hours.
- The annual demand for product B is 2000 units, with a batch size of 40 units. The standard processing time for B is 0.8 hours/unit, and the standard setup time is 8 hours.

How many new milling machines are required if Stout does not resort to any short-term capacity options?

A. No new machines
B. 1 or 2 new machines
C. 3 or 4 new machines
D. More than 4 new machines

Answer :

Final answer:

Stout Manufacturing would require 3 new milling machines to meet the demand without resorting to short-term capacity solutions.

Explanation:

The calculation for the number of new milling machines required at Stout Manufacturing is essentially a capacity planning problem. We first need to calculate the total processing time for both products. For product A, this is 3000 units * 0.5 hours/unit = 1500 hours, and for product B it is 2000 units * 0.8 hours/unit = 1600 hours.

The total time then is 3100 hours, which includes the processing time. Adding setup times, we get 150 hours for A (3000 units/20 units/batch * 2 hours/setup) and 400 hours for B (2000 units/40 units/batch * 8 hours/setup), totaling to 550 hours. Consequently, the total time, including processing and setup, is 3650 hours

Next, we need to consider the capacity cushion. Management wants a capacity cushion of 15 percent, so the total time needs to be divided by (1 - 0.15) = 0.85, giving us a total of 4294 hours. The plant operates eight hours a day, five days a week, and 50 weeks a year, so the total available time is 8 hours/day * 5 days/week * 50 weeks/year = 2000 hours/year. Consequently, Stout Manufacturing would need 4294/2000 = 2.147, in other words, 3 new machines to meet demand without resorting to short-term capacity solutions.

Learn more about Capacity here:

https://brainly.com/question/34007470

#SPJ11