Answer :
To calculate the direct labor variance, we need to compare the actual direct labor cost with the standard direct labor cost.
Standard direct labor cost = Standard rate per hour × Standard hours worked
Standard direct labor cost = $15 per hour × 2 hours per unit × 2000 units = $60,000
Actual direct labor cost = $59,200
Now, we can calculate the direct labor variance:
Direct Labor Variance = Actual Direct Labor Cost - Standard Direct Labor Cost
Direct Labor Variance = $59,200 - $60,000 = -$800
The negative sign indicates an unfavorable variance, meaning that the actual direct labor cost exceeded the standard direct labor cost by $800. This suggests that the labor cost was higher than expected, and further analysis may be needed to identify the reasons for the variance and take corrective actions if necessary.
Learn more about Direct labor variance
https://brainly.com/question/31804141
#SPJ11