It takes 12 men 5 days to complete a job.

(a) Work out how many days it would take 3 men to complete the same job.

Explanation needed for the answer, which is 20 days.

Answer :

kensley1489 kensley1489
  • 08-12-2023
12 men, 5 days.
If you divide the amount of laborers by 4, you must multiply the time it takes by 4. Thus 12/4=3 men and 5*4= 20 days.
Answer Link

Other Questions

What is the message being giving by this cartoon? What does each
You paddle a canoe with a force of 156 N. You and
What is the volume of the box in cubic inches? A. 65.5
How do teleplays like "The Monsters Are Due On Maple Street" provide
Which of the following is equal to the fraction below? [tex]\left(\frac{4}{5}\right)^6[/tex] A.
What is seen as the album where The Beatles became The Beatles?
How can 10% of 82 be used to determine 60% of 82?
A trader in Babylon offers to sell you a blanket for 20
What is Wade's login passphrase while he is in Columbus?
Constructivism emphasizes the: Question 42 options: A. Subjective construction of reality B.
What is the length of a rectangle with a width of 16
Calculate the molar mass of the unknown compound. An aqueous solution containing
A collection of [tex]6.25 \times 10^{18}[/tex] electrons has the charge of:
The patient is to receive 20 mEq of KCl (potassium chloride). The
Which angle measure is a complement of an angle whose measure is