Answer :
After crashing Activity F in Project Ace, the Project Duration is 26 and the Total Direct Cost is 30.Crashing Activity F means reducing its duration to the crash time, which is 1 week.Correct option is a. 26 and 30.
By crashing Activity F, the duration of the project is reduced by 1 week. Therefore, the Project Duration becomes 26 weeks. Total Direct Cost refers to the cost incurred by completing all the activities in the project. Since Activity F is being crashed, additional resources and costs are required. The cost of crashing Activity F is 3 units per week. By crashing it for 1 week, the Total Direct Cost increases by 3 units. Therefore, the Total Direct Cost becomes 30 units.
In conclusion, after crashing Activity F in Project Ace, the Project Duration is 26 weeks and the Total Direct Cost is 30 units. Therefore, the correct answer is option a. 26 and 30.
To learn more about Crashing Activity click here : brainly.com/question/32604845
#SPJ11